Guatemala: CIFI-01/ Hidro Santa Cruz

Date Filed
15 Jul 2015
Status
Open
Phase
Compliance
Country
Guatemala

Case Tracker

Eligibility
Eligibility
Assessment
Transferred
Assessment
Dispute Resolution
Compliance
Appraisal
Investigation
Monitoring
CURRENT Status
Monitoring (COMPLIANCE)

Complaint Overview

Complainant

Local residents of Santa Cruz.

Concerns

Community health & safety, information disclosure & consultation, indigenous people, cultural heritage.

Cross-Cutting Issues
Risk Management Community Health and Safety Land Resettlement Indigenous Peoples Land Water Women Social Order / Conflict Coercion Violence / Abuse GBVH Loss of Life Project Benefits IFC/MIGA Due Diligence IFC/MIGA Supervision

Project Information

Region
Latin America & the Caribbean
Institution
IFC
Name & Number
CIFI 26031
Company
Corporacion Interamericana para el Financiamiento
Sector
Financial Markets
Department
Global Practice - Finance & Markets
Category
FI
Commitment

$20 million A loan & $10 million equity investment

Synopsis

Project Overview

Corporación Interamericana para el Financiamiento de Infraestructura (CIFI) was established in 2001 as a non-banking financial institution to provide financing to small and medium infrastructure projects across Latin America and the Caribbean. IFC made equity and debt investments in CIFI in 2008. CIFI made an investment in the Hidro Santa Cruz (HSC) for the construction of the Canbalam hydropower plant (“the project”) in Santa Cruz Barillas, Huehuetenango, Guatemala in 2011.  Project construction commenced in early 2012, however, it was suspended soon afterward following an escalation of community protests. CIFI ended its investment in late 2015, and the project was abandoned in December 2016.

Complaint

In July 2015, a group of community representatives filed a complaint on behalf of themselves and other community members in Santa Cruz Barillas, alleging that the project was never properly consulted with the indigenous communities and that community members’ opposition to the project had been met with violence and repression on the part of the company and the government. In particular, they note a violent incident on May 1, 2012, where one community member was shot dead and two others injured. The complainants maintain that one of the perpetrators was a security guard hired by the project. HSC acknowledges that one of the two individuals who was charged with the shooting had worked for the project’s security contractor but denies any involvement in the incident. The May 2012 incident led to a violent protest involving hundreds of local people following which the Government of Guatemala declared a state of siege in Santa Cruz Barillas and mobilized police and military to the area for almost three weeks.

CAO Action

CAO found the complaint eligible for further assessment in August 2015 and an assessment visit was conducted in October 2015. During the assessment, the company expressed its willingness to participate in a dispute resolution process convened by CAO, however, the complainants felt that it was not worth initiating a new dialogue process with the project operator in light of the violent events and damages suffered. By CAO’s Operational Guidelines, the case was referred to CAO’s compliance function.

CAO released a compliance appraisal report in August 2016. The compliance appraisal concluded that an investigation was warranted in response to this complaint.

CAO completed its compliance investigation in December 2018 when it was sent, together with IFC’s response, to the President of the World Bank Group for clearance. CAO’s report and IFC’s response were discussed at a meeting of the IFC Board in February 2020 subsequent to which IFC revised its response. IFC’s revised response to the investigation is dated April 2020, the April 2020 response includes information that was not presented to the CAO in the course of the investigation.

In June 2020, CAO’s compliance investigation report and IFC’s response were cleared for release by the President of the World Bank Group. In its report, CAO made several non-compliance findings in relation to IFC’s review and supervision of its investment including its response to the sub-project incident.

IFC Pre-investment Review
CAO found that IFC’s pre-investment environmental and social (E&S) review of the company’s E&S management system (ESMS) was not commensurate to risk. CAO identified shortcomings in IFC’s assessment of (a) the client’s track record of ESMS implementation, and (b) the client’s capacity to implement its ESMS to IFC standards.

IFC Response and Support to the Client in relation to the Sub-project
IFC’s lack of oversight in ensuring the client was implementing an adequate ESMS—one that was sufficient to assess and monitor risks and impacts arising from investments in projects such as Canbalam I—contributed to a situation in which project activities were allowed to commence in advance of an adequate risk assessment and implementation of mitigation measures envisaged by the Performance Standards.

Following the violent incidents of May 2012, the client suspended disbursements to the project and notified IFC. Where IFC is notified of a serious incident at the project level, IFC has a duty to respond as per its own E&S procedures. This includes requirements to ensure that the root cause of the incident is assessed, and measures put in place to prevent reoccurrence.

IFC, however, did not engage with the client in relation to the project or the violent incident as required by its E&S procedures. CAO finds that IFC did not comply with its procedures on responding to serious incidents, nor did it take measures needed to ensure that the client’s response reflected Performance Standards requirements to address project impacts throughout the project cycle including at project closure.

Ultimately, in November 2015, CIFI terminated its loan to the project developer, and the project was abandoned in December 2016.

The 2006 Sustainability Policy which was in force at the time of investment provides that efforts to carry out its investment activities in a manner that “do no harm” to people or the environment are central to IFC’s development mission. The Policy also commits IFC to “ensuring that the costs of economic development do not fall disproportionately on those who are poor and vulnerable.” Where adverse project impacts do occur, the Policy and PS1 provide that IFC will work with its client to ensure that impacts are assessed, reduced, mitigated, or compensated for, as appropriate.

The complainants maintain that the project has resulted in adverse social impacts on their communities. In particular, they claim that the project led to the escalation of project-related conflict, resulted in the death of one community member, left two community members seriously injured, and led to the detainment of seventeen other community members. They assert that traditional access to land and natural resources remains limited due to the construction of a perimeter fence around the project site.

While the project was abandoned in December 2016, the available evidence supports the complainants’ assertion that residual impacts remain. Though aware of these impacts during the period of financing, IFC did not engage with its client to ensure that residual impacts of the project were assessed, reduced, mitigated, or compensated for, as appropriate, including at project closure, as required by IFC's Performance Standards and Sustainability Policy.

Status

On June 10, 2020, CAO released its compliance investigation report and IFC’s response. IFC provided a Spanish version of its executive summary on August 12, 2020. On September 23, 2020, CAO published a summary of the investigation report in Q'anjob'al. 

CAO is monitoring IFC’s response to the non-compliance findings made in this investigation. 

Status as of September 23, 2020

 

Case Documents

  • Complaint
    CIFI Complaint
    Jul 01, 2015
    English
    CIFI Complaint
    Assessment Report(s)
    CAO Assessment Report CIFI
    May 18, 2016
    English
    CAO Assessment Report CIFI
    CAO Assessment Report CIFI
    May 18, 2016
    Spanish
    CAO Assessment Report CIFI
    CAO Assessment Report CIFI
    May 18, 2016
    Qanjobal
    CAO Assessment Report CIFI
    IFC formal Response
    May 01, 2016
    English
    IFC formal Response
  • Compliance

    Appraisal Report(s)
    CAO Compliance Appraisal Report
    Aug 12, 2016
    English
    CAO Compliance Appraisal Report
    CAO Compliance Appraisal Report
    Aug 12, 2016
    Spanish
    CAO Compliance Appraisal Report
    CAO Compliance Appraisal Report
    Aug 12, 2016
    Qanjabal
    CAO Compliance Appraisal Report
    Investigation Report(s)
    CAO Compliance Investigation Report
    Dec 19, 2018
    English
    CAO Compliance Investigation Report
    Investigacion de la CAO relativa al desempeno
    Dec 19, 2018
    Spanish
    Investigacion de la CAO relativa al desempeno
    CAO Investigation Report Summary
    Sep 23, 2020
    Qanjabal
    CAO Investigation Report Summary
    IFC Management Response to the CAO
    Apr 23, 2020
    English
    IFC Management Response to the CAO
    Respuesta De La Administración Al Informe
    Apr 23, 2020
    Spanish
    Respuesta De La Administración Al Informe
    Terms of Reference
    Jan 03, 2017
    English
    Terms of Reference
    Terms of Reference
    Jan 03, 2017
    Spanish
    Terms of Reference
  • Mailchimp Survey

     

    We Value Your Feedback

    Thank you for visiting CAO’s new website. Help us improve your experience by taking our short survey.

    Give Feedback No thanks