Uganda: Bujagali Energy-05/Bujagali

Date Filed
16 May 2011
Status
Closed
Phase
Dispute Resolution (DR), Compliance
Country
Uganda

Case Tracker

Eligibility
Eligibility
Assessment
Assessment
Dispute Resolution
Dispute Resolution
Monitoring
Closed
Compliance
Appraisal
Closed
Investigation
CURRENT Status
Investigation (COMPLIANCE)

Complaint Overview

Complainant

Local community members

Concerns

Land acquisition, compensation, impacts to health and infrastructure

Cross-Cutting Issues
Risk Management Community Health and Safety Land Resettlement Biodiversity Land Water Women Loss of Life Loss of Livelihoods Private / Personal Property Damage Unfulfilled Commitments

Project Information

Region
Africa
Institution
IFC/MIGA
Name & Number
Bujagali Energy Ltd 24408 (IFC) & 6732 (MIGA)
Company
Bujagali Energy (IFC); World Power Holdings (MIGA)
Sector
Infrastructure
Department
Infrastructure
Category
A
Commitment

$100m A & C loans (IFC), $115m guarantee (MIGA)

Synopsis

Project Overview

The Bujagali Energy project involves the development, construction, and maintenance of a run-of-the-river power plant with a capacity of up to 250 MW on the River Nile in Uganda.  Bujagali Energy Limited also manages the construction of approximately 100 kilometers of 132 kV transmission line on behalf of the Uganda Electricity Transmission Company Ltd. to improve transfer of electricity from the plant. Bujagali Energy Ltd is owned by Industrial Promotion Services (Kenya) Ltd. – the industrial development arm of the Aga Khan Fund for Economic Development and SG Bujagali Holdings, Ltd., an affiliate of Sithe Global Power LLC (US). IFC and MIGA are supporting the $750 million project along with several other international financial institutions, including the International Development Association, African Development Bank and European Investment Bank.  IFC’s investment comprises $100 million in A and C loans, and MIGA issued a $115 million guarantee to World Power Holdings Luxembourg S.à.r.l., a subsidiary of Sithe Global Power, for its investment in the project.

Complaint

In May 2011, CAO received a fifth complaint related to the Bujagali project.  The complaint was submitted on behalf of community members who claimed to be affected by the construction of the Bujagali dam and the transmission line “interconnection” project.  The complainants’ raised the following concerns: 1. Loss of livelihood due to the project’s destruction of Bujagali Falls and consequent impact on tourism; 2. Damage caused by blasting during construction and consequent impacts on health, homes, and livestock; and 3. The flawed compensation process undertaken during the project’s acquisition of land for power transmission lines.

Action

Assessment:

CAO found the complaint eligible for assessment in June 2011, and embarked on an assessment to gain a better understanding of the issues raised.  During the assessment CAO met on several occasions with key stakeholders, and the complainants and company opted to proceed with a CAO dispute resolution process.  The assessment report was completed in December 2011 and is available in English and Luganda at the link below.

Dispute resolution:

The dispute resolution process started in December 2011, and during preliminary meetings the stakeholders agreed to address the complaint through dividing the process into the three themes: 1. Loss of livelihood; 2. Damage caused by blasting during; and 3. Compensation for loss of land.  Additionally, as some of the complainants had also submitted complaints to the EIB-CM related to the blasting impacts (2.), the parties agreed that rather than launching separate dispute resolution processes related to the blasting, an EIB-CM-led mediation would address the blasting damage, while CAO-led dispute resolution processes would focus on the livelihood and land compensation concerns.

Regarding the loss of livelihoods from the destruction of Bujagali Falls, when the dispute resolution process began the company entered into direct negotiations with the local tourism operators and reached written agreements over compensation, which were implemented during April and May 2012.  CAO monitored implementation of the agreements and, in September 2012, verified with all parties that the agreements had been fulfilled and issues resolved to their satisfaction.

Regarding the damage cause by blasting, a mediation process facilitated by the EIB-CM was initiated in March 2012, and culminated in a ‘Mediation Solution’ in November 2012, which was implemented during 2014 and early 2015.  The CAO complainants were not satisfied with the Mediation Solution implemented from the EIB-CM process and requested CAO assistance in further resolution.  However, as the company was not willing to engage in a further mediation process, and giving the voluntary nature of CAO dispute resolution, in January  2017, the outstanding issues concerning blasting impacts were transferred to CAO compliance for appraisal (details below).

Regarding the land compensation, through CAO-facilitated dialogue complainants' representatives and the Uganda Electricity Transmission Company Ltd (UETCL) reached and signed a Mediation Agreement in April 2015, with a group of 514 complainants, the '557 Group', which was subsequently adopted by the High Court of Uganda as a Judgment of the Court in May 2015.  CAO monitored the implementation of the agreement and noted that while UETCL did not fulfill its original commitment to handle compensation no later than July 31, 2015, implementation of the agreement was completed in April 2017.  Another group of 16 complainants (Non-557) who were not part of the lawsuit signed an agreement with UETCL in April 2017. Compensation was made to all Non-557 complainants in June 2017. An individual land compensation agreement was signed with UETCL in June 2017. The agreement was submitted and approved by the UETCL Board in November 2017. Following their Board approval, UETCL  issued full payment to the complainant in April 2018, thereby bringing the dispute to a successful closure.

CAO released its Monitoring Report on January 15, 2016, which covers the full dispute resolution process addressing the three themes.  The monitoring report can be found under "view Documents" below.

Compliance appraisal regarding blasting impacts:

In January 2017, CAO initiated its compliance appraisal regarding the blasting impacts.   CAO released a compliance appraisal report on March 13, 2017, concluding that an investigation of IFC/MIGA's performance in relation to blasting impacts of the project was not warranted. This aspect of the case has been closed.

 

Status

This case is now closed following monitoring of the agreements reached by the parties regarding loss of livelihoods and land compensation, and following the compliance appraisal regarding the blasting impacts.

Status as of September 26, 2018

Case Documents

  • Dispute Resolution

    Complaint
    Letter of complaint
    May 10, 2011
    English
    Letter of complaint
    Assessment Report(s)
    Ombudsman Assessment Report
    Dec 01, 2011
    English
    Ombudsman Assessment Report
    Ombudsman Assessment Repor
    Dec 01, 2011
    Luganda
    Ombudsman Assessment Repor
    IFC Response, CAO Ombudsman Assessment Reports
    Feb 03, 2012
    English
    IFC Response, CAO Ombudsman Assessment Reports
    Agreement(s)
    Outcome of Mediation Process
    May 31, 2013
    English
    Outcome of Mediation Process
    Interim Ombudsman / Dispute Resolution Monitoring Report
    Jan 01, 2016
    English
    Interim Ombudsman / Dispute Resolution Monitoring Report
    Annex 1 - Settlement Agreement
    Mar 01, 2015
    English
    Annex 1 - Settlement Agreement
    Close-out Report(s)
    Dispute Resolution Conclusion Report Bujagali-05
    Jun 01, 2018
    English
    Dispute Resolution Conclusion Report Bujagali-05
    Dispute Resolution Conclusion Report Bujagali-05
    Jun 01, 2018
    Luganda
    Dispute Resolution Conclusion Report Bujagali-05
  • Appraisal Report(s)
    CAO Compliance Appraisal Report, Bujagali-05
    Mar 13, 2017
    English
    CAO Compliance Appraisal Report, Bujagali-05
  • Mailchimp Survey

     

    We Value Your Feedback

    Thank you for visiting CAO’s new website. Help us improve your experience by taking our short survey.

    Give Feedback No thanks